01 / PROJECT BACKGROUND
A home, a real experience.
Adriana R.’s house in Cahul, Republic of Moldova, measures 81 m² including its veranda. It was handed over in November 2025 as a structural shell with metal roofing installed. SIPROM handled design, kit production, transport and assembly, while the owner independently arranged the foundation and subsequent work.
SIPROM prepared the planning permission documentation and technical design, then manufactured and assembled the house. The owner independently arranged the foundation and selected local teams for PVC windows and doors, the façade, building services and interior finishes, to spread costs over several stages.
The reference model is the single-storey house with veranda in the SIPROM catalogue, with two bedrooms, a bathroom and a living area with kitchen. Its area is 81 m², including the approximately 12.15 m² veranda, according to the catalogue model. The enclosed area calculated from the external outline is approximately 68.85 m²; this is not the usable floor area.
02 / CONSTRUCTION DETAILS
The solution chosen for this house.
Structure and layout
A single-storey house with a covered veranda, built in Cahul. The catalogue model places two bedrooms, a bathroom and a living area with kitchen on one level.
Materials and dimensions
The walls are 2.50 m high. Exterior wall and ceiling panels are 175 mm (17.5 cm) thick, while interior wall panels are 125 mm (12.5 cm) thick. These dimensions describe the Cahul project; the solution for other houses is determined during design.
The handover stage
SIPROM handed over the structural shell with metal roofing installed in November 2025. PVC windows and doors, the façade, building services and interior finishes were arranged separately by the owner. The finished image in the design section is a proposed final appearance.
PROJECT TIMELINE
From design to assembly.
The reported durations for the Cahul house were similar to those for the Brașov project. The figures below are approximate.
- Design · approximately one month
SIPROM completed the planning permission documentation and technical design.
- Planning permission · approximately three months
The permission stage depends on the authorities and documentation required for the site.
- Foundation · approximately two weeks
The owner independently organised foundation construction.
- Preparation for assembly · approximately four weeks
There was a waiting period after the foundation was poured and before assembly. The SIPROM kit was produced during this time, so the stages overlapped.
- Structural shell assembly · approximately 12 working days
After delivery and foundation preparation, the SIPROM team assembled the house structure.
- Metal roofing · approximately two days
Installing the metal roofing completed the structural shell handover stage. The house was handed over in November 2025.
Planning permission and foundation construction depend on factors outside SIPROM’s control. Time on site should be distinguished from the overall project duration; another house’s timeline will depend on its design and location.