01 / PROJECT BACKGROUND
A home taking shape.
Handed over in July 2026, Vlad G’s house in Brașov was built in stages. SIPROM completed the planning permission design, technical design, kit production and structural shell assembly, including installation of the metal roofing.
The 3D models show the structural solution, while the site photographs follow wall assembly and roof construction. The final aerial views document the handover stage, before windows, doors and finishes.
In his review, the owner praises the speed of the work, the team’s reliability and the materials used. His account adds the homeowner’s perspective to the photographs.
The owner arranged the foundation independently. After SIPROM’s handover, he chose to manage the PVC windows and doors, façade, building services and interior finishes with local teams to optimise costs and spread the investment over several stages.
The completed house has a total gross floor area of 172.10 m² and a usable floor area of 140.10 m², matching the catalogue model, with three bedrooms and three bathrooms. The ground floor contains the living area, kitchen with pantry and utility room; the bedrooms are upstairs. View the model and floor areas in the SIPROM catalogue ↗
02 / CONSTRUCTION DETAILS
A structure engineered for this project.
2.80 m wall height
The walls in this project are 2.80 m high. This measurement refers to the structural walls; the finished clear height depends on the final floor and ceiling build-ups.
Thicknesses determined by structural calculations
The exterior walls are 17.5 cm thick and the floor panels are 22.5 cm thick. Interior walls are 12.5 or 17.5 cm thick, depending on the requirements of the structural calculations.
Structural shell handover with metal roofing
The final photographs show the assembled structure and installed metal roof covering. This configuration belongs to the project shown; the scope for each house is defined in its individual quotation.
THE PROJECT’S ACTUAL TIMELINE
From design to an assembled home.
After kit delivery, structural shell assembly took 12 working days, followed by a further 2 days to install the metal roofing.
- Approximately 1 month — design
SIPROM completed the planning permission design and technical design.
- 3 months — planning permission
The permission stage depended on procedures and factors outside SIPROM’s control.
- 2 weeks — foundation construction
The owner arranged the foundation independently.
- 4 weeks — waiting period after pouring the concrete
For this project, four weeks were allowed before house assembly. Kit production took place during the same period.
- 12 working days — structural shell assembly
After delivery, the SIPROM team assembled the house structure.
- A further 2 days — metal roofing
The house was handed over as a structural shell with metal roofing installed.
Prefabrication enabled rapid on-site assembly. Planning permission and foundation construction followed timelines affected by factors outside SIPROM’s control. The durations above apply to this project and are not guaranteed deadlines for every house; the required interval before assembly on the foundation is determined by the design and construction conditions.